WTP at the Opole Power Plant - progress on site
03.10.2016
Intensive assembly work at the Water Treatment Plant in Opole Power Plant is in progress.
The Coagulation and Flotation Building is currently under construction - among other things, the installation of ventilation and rain drainage system, assembly of Dn1000 pipelines, self- cleaning filters and delivery and assembly of saturators, scrapers and pumps. In the Filtration Building the Dn1200 and Dn1000 pipelines are being installed, while in the Pump Building technological pipelines are installed.